Container Scheduling Proposals

Container Scheduling Proposals
Keywords: container scheduling, logistics optimization, cold chain management, citrus industry, reefer containers, export compliance, pallet configuration, ventilation systems

1. Container Supply

1.1 Communication Gaps

Communication between shipping lines and industry organisations about long-term crop projections, seasonal estimates, and short-term crop changes is lacking and can impact container supply (short and long term).
Actions:

  • Initiate regular pre-season communication with shipping lines
  • Regular crop updates to be communicated to shipping lines
    Responsible: Hortgro
    Priority: C
    Notes: Hortgro to initiate a formal pre-season meeting with shipping lines to discuss crop forecasts and issues of mutual concern.

1.2 Inflated Exporter Demands

Exporters tend to inflate demands during shortages, leading to late cancellations and last-minute re-allocation of containers.
Actions:

  • Shipping lines and booking agents to introduce incentives for accurate forecasts
  • Include in pre-season discussions
    Responsible: Hortgro
    Priority: B
    Notes: Last-minute market switches aggravate the problem. Hortgro to include the issue in pre-seasonal discussion.

2. Container Availability

2.1 Urban Traffic Delays

Pick-up times of empty containers coincide with peak urban traffic, causing late arrivals at loading points.
Actions:

  • Incentivise Bellcon container depot concept
  • Investigate feasibility of earlier depot opening times
    Responsible: Project (Generic)
    Priority: A+
    Notes: Andy Cornell to circulate trial results. Discuss night loading.

2.2 Container Lifespan & Maintenance

Recessionary trade conditions may force shipping lines to extend container lifespan, risking cold chain integrity.
Actions:

  • Obtain and analyse factual information (PPECB)
  • Discuss supply of newer containers with shipping lines
    Responsible: PPECB, Hortgro
    Priority: C
    Notes: Request younger containers for sensitive fruit, especially during high ambient temperatures.

2.3 Container Rejection at Loading Points

Some containers slip through inspection and are rejected at loading points.
Actions:

  • Compile and analyse records (ongoing)
  • Include plug points in loading point approval
  • Loading points to have checklists for set points, cables, etc.
  • Charge shipping lines if set points must be corrected at loading point
    Responsible: PPECB
    Priority: B

2.4 Depot Operator Relations

Poor relations/attitude of some empty depot operators hinder urgent requests.
Actions:

  • Educate depot staff on fruit knowledge and urgency
    Responsible: PAG
    Priority: C

2.4 Fruit Specification

2.4.1 Inaccurate Stock Figures

Late transfer of electronic files or wrong assumptions about fruit temperature cause late bookings and delays.
Actions:

  • Service level agreements (SLAs) between cold stores and exporters
  • Basic SLA as guideline for industry
    Responsible: Packhouse cold stores
    Priority: B

2.4.2 IT System Incompatibility

Incompatibility of IT systems causes inaccurate stock records.
Actions:

  • Take corrective action where incompatibility is identified
    Responsible: Packhouse cold stores
    Priority: B

2.4.3 Poor Cut-off Discipline

Poor discipline regarding cut-off times puts pressure on scheduling.
Actions:

  • SOPs between exporter and booking agent to spell out cut-off times
  • Enforce cut-off times and/or consider incentives
    Responsible: Booking agent
    Priority: A

2.4.4 Lack of Fruit/Process Knowledge

A lack of basic fruit and process knowledge causes poor communication and urgency.
Actions:

  • Identify, create, publicise, and motivate
    Responsible: PAG
    Priority: A+

2.4.5 24/7 Availability

Attitude and willingness to be available 24/7 is required for corrective action.
Actions:

  • SLA between exporter and agent to spell out criteria
    Responsible: Packhouse cold store
    Priority: B

2.4.6 Last Day Cancellations

Cancellation of booked containers on the last day of stack leads to inefficiency.
Actions:

  • Incentives from shipping lines and agents
    Responsible: Booking Agents
    Priority: A

2.5 Contracting Transport

2.5.1 Truck Reliability

Reliability and roadworthiness of trucks are not enforced.
Actions:

  • Feedback and follow-up by cold stores
  • Include undertakings from transporter in SLA
  • Prepare checklist for loading point
    Responsible: Loading points, Agents, PAG
    Priority: B

2.5.2 Incorrect Cargo Weight

Incorrect cargo weight declaration is a serious problem.
Actions:

  • Use standard weight lists
  • Loading point to check and correct declared weight
  • Spell out seriousness to agents and loading points
    Responsible: Booking agents, Loading points, Shipping lines
    Priority: A

2.5.3 Overweight Containers

Overweight containers stopped at weighbridges cause delays and losses.
Actions:

  • Cooperation between driver and loading point
  • Evaluate feasibility of self-control system
    Responsible: Booking agents, Hortgro
    Priority: B

2.5.4 Poor Delay Communication

Poor communication of delays prevents proactive steps.
Actions:

  • Strict discipline for non-compliance by drivers
  • Loading points to report non-compliance
  • Include in SLA
    Responsible: Transporters, Loading points, Booking agents
    Priority: A

2.5.5 Unreliable Transport Contractors

Unreliable contractors disrupt schedules.
Actions:

  • Report and blacklist unreliable transporters
  • Record deviations
    Responsible: Loading point
    Priority: A

2.5.6 CTO Process

The CTO (Container Terminal Order) process is time-consuming and outdated.
Actions:

  • Evaluate impact of new Transnet Navis system
  • Initiate development/enhancement if needed
  • PAG discussions with Transnet
    Responsible: Generic, Project, PAG
    Priority: A+

2.5.7 Loading Timeslots

Realistic loading timeslots are often lacking.
Actions:

  • Enforce realistic loading times
  • Transporter discipline to stick to timeslots
  • Consider financial incentives
    Responsible: Booking agent, PPECB, Loading Points
    Priority: A+

2.5.8 TTTs (Time Temperature Tolerances)

TTTs are not always adhered to.
Actions:

  • Monitor TTTs more accurately (PPECB)
  • Evaluate new technology for temperature monitoring
    Responsible: PAG
    Priority: A

2.5.9 Delays to Power Coupling

Delays from loading to coupling containers to power points threaten cold chain.
Actions:

  • Improve monitoring system
  • Follow-up action
    Responsible: PPECB
    Priority: A+

2.5.10 Last Day Bookings

Bulk bookings on the last day of stack cause inefficiency.
Actions:

  • Spell out importance of even bookings
  • Identify/evaluate incentives to reduce last day loadings
    Responsible: PAG
    Priority: A+

2.5.11 Dual Loads

Increase in dual loads requires special procedures.
Actions:

  • Evaluate rules for dual loads
  • Compile guidelines for pome fruit
    Responsible: PAG, PPECB
    Priority: A

2.5.12 Container Cable Theft

Cable theft is a serious and disruptive issue.
Actions:

  • Drivers to take accountability
  • Include in loading point checklist
    Responsible: Loading Points
    Priority: B

2.5.13 Vehicle Exhaust Position

Exhaust pipes can cause fumes to enter containers.
Actions:

  • All vehicles to comply
  • Include in SLA
  • Check vehicles at empty depot gate and loading point
    Responsible: Transporter, Agent, Empty depot, Loading Point
    Priority: B

3. Fruit Loading

3.1 PPECB Availability

PPECB officials cannot always be present at all loading points, causing delays.
Actions:

  • Evaluate auditing vs. monitoring role by PPECB
  • Improve communication between PPECB and loading points
    Responsible: PPECB, PAG
    Priority: A+

3.2 Lack of Cooled Airlocks

Most cold stores lack cooled airlocks, preventing effective pre-staging.
Actions:

  • Motivate provision of airlocks
  • Evaluate alternatives (e.g., pallet shrouds, holding stores)
  • Effective communication
    Responsible: PAG, Loading points
    Priority: B

3.3 Loading Point Accountability

Loading points not always accountable for container condition and fruit protocols.
Actions:

  • Spell out responsibilities
  • Implement control system (checklist)
    Responsible: PAG
    Priority: B

3.4 Power Plug Points

Most cold stores lack power plug points to check container temperature.
Actions:

  • Motivate installation of plug points
    Responsible: PAG
    Priority: A

3.5 Random Access to Pallets

Cold stores not geared for random access to individual pallets, causing delays.
Actions:

  • Apply sound cold store management
  • Insist on early specifications
  • Effective pallet replacement procedures
    Responsible: Loading points, Exporter
    Priority: B

3.6 Hi-Cube Pallet Handling

Older cold stores not converted for hi-cube pallets.
Actions:

  • Upgrade facilities
    Responsible: PAG
    Priority: B

3.7 Cold Sterilisation Markets

Increase in markets requiring cold sterilisation; PPECB presence required.
Actions:

  • Early advice
  • Proactive arrangements with PPECB/DAFF
    Responsible: Booking agent
    Priority: A

3.8 IT System Compatibility

IT systems at exporter and cold stores not always compatible.
Actions:

  • Evaluate seriousness
    Responsible: PAG
    Priority: A

3.9 Poor Stock Management

Leads to costly delays.
Actions:

  • Loading points to accept cost for delays
  • Monitor delays
    Responsible: Loading points, Booking agent
    Priority: A

3.10 Disruptive Quality Control

Quality control during loading is disruptive.
Actions:

  • Do quality control prior to loading
    Responsible: Loading points
    Priority: C

3.11 Poor Communication of Delays

Poor communication of delayed cooling or stock differences causes futile trips/delays.
Actions:

  • Early advice of deviations
  • Proactive steps
    Responsible: Loading points, Booking agent
    Priority: C

3.12 Lack of Training

Training in basic fruit knowledge and processes is lacking.
Actions:

  • Identify existing training tools
  • Advise/motivate role-players
    Responsible: PAG
    Priority: A+

3.13 Overloading Accountability

Loading points do not realise accountability for overloading containers.
Actions:

  • Spell out consequences and accountability
    Responsible: PAG
    Priority: C

3.14 Peak Season Cooling Capacity

Peak season puts cooling capacity to the test.
Actions:

  • Effective capacity planning
  • Effective communication
  • Adjust cooling rate criteria
    Responsible: Loading points, Exporters
    Priority: A

3.15 Full Cold Stores

Full cold stores make locating specific pallets difficult.
Actions:

  • Effective cold store management
  • Pre-staging under cool conditions
  • Practical pallet replacement procedure
    Responsible: Loading points, Exporter
    Priority: C

3.16 Lack of Loading Statistics Analysis

Lack of analysis leads to missed corrective steps.
Actions:

  • Good recordkeeping
  • Effective analysis and follow-up
    Responsible: Loading points
    Priority: C

4. Container Shipping

4.1 Driver Sensitivity to Cold Chain

Drivers not always sensitive to cold chain integrity, causing TTT to be exceeded.
Actions:

  • Basic driver training
  • Monitor TTT
  • Transporter to accept liability
    Responsible: Transporter, PPECB
    Priority: A

4.2 Stack Time Changes

Reaction to changed stack times sometimes lacking, especially after hours.
Actions:

  • Operational staff contactable 24/7 (include in SLA)
  • Timely action
    Responsible: Booking agent
    Priority: B

4.3 Vessel By-Pass Notification

Late notification of vessels by-passing port disrupts scheduling.
Actions:

  • Shipping lines to be aware of consequences
  • Proactive anticipation
  • Prepare shipping education lecture
    Responsible: Shipping lines, Booking agent
    Priority: C

4.4 Terminal Standing Times

Excessive standing times at terminals during tea breaks and shift changes.
Actions:

  • Evaluate situation
  • Discuss solutions with terminal managers
    Responsible: PAG
    Priority: C

Rating Structure

  • Priority A+: Issue is very important and needs to be addressed as a high priority
  • Priority A: Issue is important and needs to be addressed
  • Priority B: Issue needs attention but is not critical
  • Priority C: Issue is a concern or can be addressed relatively quickly